{"id":6101,"date":"2022-04-28T09:05:20","date_gmt":"2022-04-28T15:05:20","guid":{"rendered":"https:\/\/www.flatironcorp.com\/?p=6101"},"modified":"2022-04-28T09:25:14","modified_gmt":"2022-04-28T15:25:14","slug":"flatiron-successfully-installs-farrell-creek-bridge-girders-connecting-highway-29-in-british-columbia","status":"publish","type":"post","link":"https:\/\/www.flatironcorp.com\/news\/flatiron-successfully-installs-farrell-creek-bridge-girders-connecting-highway-29-in-british-columbia\/","title":{"rendered":"Flatiron Successfully Installs Farrell Creek Bridge Girders Connecting Highway 29 in British Columbia"},"content":{"rendered":"

[vc_row][vc_column][vc_column_text]We\u2019re excited to share another important milestone achieved by Flatiron\u2019s Highway 29 – Farrell Creek Project team. On April 7, 2022, the Flatiron team successfully completed the erection of the steel bridge girders.<\/p>\n

The girder erection work started in late January 2022, following the construction of the substructure completed in October 2021. In about two and a half months, the team successfully placed 39 steel girders on top of the piers over Farrell Creek, connecting Highway 29 from the east to west.<\/p>\n

The following is a snapshot of some of the highlights of the girder erection work:<\/p>\n